Hiranandani Hinjewadi Construction Status
Comprehensive civil engineering progress, milestone updates, and possession timeline for the 105-acre neoclassical master township in North Hinjewadi, Pune.
The Colosseum (Phase 4)
MahaRERA: PR1260002600818
Foundational piling and double basement excavation 100% completed. Structural podium casting underway. Monolithic shear walls being poured with German aluminium formwork.
Sector Arcadia
MahaRERA: PR1260002500600
Towers 1, 2, and 3 progressing at a rapid 12-day slab cycle. Mid-level civil structural completion reached. Plumbing and electrical conduit rough-ins actively underway.
Della Villa Plots & Turf Racecourse
Sanctioned Estate Layout
8-acre equestrian turf track grading complete. Sub-grade storm water drains, underground high-voltage electrical ducts, and internal 60ft arterial roads fully paved.